County approved permit plans are required on site for all inspections including reinspections.
The FINAL inspection is to be requested after all sub trades are complete and approved.
All plumbing, mechanical and electrical permit final inspections must be approved prior to the final building inspection.
Floor and ceiling insulation shall be installed. Vapor retarders must be turned towards conditioned (room) side.
The crawl space grade must meet the requirements of items #2 and #3 as listed under foundation inspection. Crawl space grade shall be free of wood and debris. Pipe and conduit holes in foundation walls shall be pointed up. The draintile discharge termination, if required shall be marked for inspection.
Screen porches, balconies, decks, and raised floor surfaces located more than 30" above the floor or grade shall have guardrails. The guardrail shall be a minimum of 36" in height and its intermediate rails shall be constructed so that a 4" diameter sphere cannot pass between them. Guardrails at stairs are permitted to allow the passage of a 4 3/8" sphere. An exception to the 4" diameter rule is the triangular space formed between the steps and the bottom member of the handrail. This space shall be constructed so that a 6" diameter sphere cannot pass between them. Stairs with a total rise 30" or greater may not have openings between the treads greater than 4". If the risers are closed or solid a "-1 " nosing is required unless the tread depth is 11" or greater measured nosing to nosing.
Guardrail post notching is not allowed.
Smoke detectors shall be installed in the required locations. (One in each bedroom, one in the immediate vicinity of the bedrooms and one on each floor of the house and not closer than 3 ft. to an HVAC return air grill, a HVAC supply vent, a bathroom with a shower, or a kitchen.) The detectors shall be interconnected; hardwired and have a battery back up.
Fireplace hearth depth, hearth extension depth, damper size, the clearance to combustible trim and the chimney termination shall meet code requirements. The top of the chimney shall extend a min. 2' higher than any portion of the building within 10', but shall not be less than 3' above the point where the chimney passes through the roof.
Exterior deck steps need to be positively attached per Henrico County policy.
Roofs and attics shall be properly cross-vented.
Interior finish material shall meet the flame-spread requirements of the code. The vapor retarder and/or insulation containment material left exposed in unfinished areas shall have a flame spread not exceeding 25 and a smoke developed index not to exceed 450.
Bath fans and dryer vents shall be vented to the outside through a louver or vent cap.
All egress doors shall be readily operable from the egress side without a key or special knowledge.
Lots shall be graded with a minimum 6" in 10' fall away from the foundation and any drainage discharge lines are to be marked.
Roof drainage systems, downspout extensions and HVAC drip line extensions may be required by the soils report and will be checked at this time.
Based on the 2006 Virginia Residential Code.